Legislation Details

File #: 26 -408    Version: 1
Type: Resolution Status: Agenda Ready
File created: 10/6/2026 In control: Board of Trustees
On agenda: 10/15/2026 Final action:
Title: Consideration of a Resolution Authorizing the Village Manager to Reject Public Bids and Procure Remote Telemetry Units for SCADA Lift Station Upgrades from Xylem Water Solutions USA, Inc. Flygt Products of Mokena, Illinois for a Total Cost Not-to-Exceed $115,000
Attachments: 1. Resolution, 2. Xylem 2026-CHI-0634 Updated
Agenda Item:
title
Consideration of a Resolution Authorizing the Village Manager to Reject Public Bids and Procure Remote Telemetry Units for SCADA Lift Station Upgrades from Xylem Water Solutions USA, Inc. Flygt Products of Mokena, Illinois for a Total Cost Not-to-Exceed $115,000
memo
Staff Contact: Monica Sarna, Public Works Director, Matt Siegel, Information Technology Director
Purpose and Actions Requested: Staff requests Village Board consideration of a resolution authorizing the Village Manager to reject all public bids and execute a purchase agreement with Xylem Water Solutions USA, Inc Flygt Products of Mokena, Illinois for remote telemetry units for the SCADA lift stations upgrades for a total cost not-to-exceed $115,000.
Budget Impact: Budgeted
Budget Fund: 100-100-150-80305, 100-100-150-60305
Strategic Priority Addressed: Reliable Infrastructure, Community Resilience

body
BACKGROUND AND ANALYSIS
The Village’s sanitary sewer system consists of approximately 40 miles of sanitary sewer main, 1,042 manholes and eight lift stations. The Village maintains separate Supervisory Control and Data Acquisition (SCADA) systems for its water production and distribution system and sanitary sewer system. These systems provide real-time monitoring, control pump operations, track system performance and waste water levels and provide alerts during unusual or emergency conditions, allowing staff to respond promptly to operational issues.
The SCADA system serving the Village’s eight sanitary sewer lift stations is particularly important for monitoring waste water levels, controlling pump operations and providing critical alarms. The existing hardware was installed more than ten years ago and several components have reached or are approaching the end of their useful life. Continued reliance on aging and obsolete components creates increasing concerns related to system reliability, operational continuity, equipment support and cybersecurity.
On August 26, 2026 s...