Agenda Item:
title
Consideration of a Resolution Authorizing the Execution of an IDOT Joint Funding Agreement and Appropriating $292,680 for the Green Bay Trail Construction Between Hazel Avenue and South Avenue
memo
Staff Contact: James Tigue, Village Engineer
Purpose and Actions Requested: Staff requests Village Board consideration of a Resolution Authorizing the Execution of an IDOT Joint Funding Agreement and Appropriating $292,680 for the Green Bay Trail Construction project between Hazel Avenue and South Avenue
Budget Impact: Budgeted
Budget Fund: 130-300-000-80120
Strategic Priority Addressed: Reliable Infrastructure, Community Resilience
body
BACKGROUND AND ANALYSIS
Approximately three miles of the Green Bay Trail traverse Glencoe between Scott Avenue and Lake Cook Road. While most of the Green Bay Trail is located on a dedicated off-street path, the trail transitions to an on-street route along Old Green Bay Road between Hazel Avenue and South Avenue.
The Green Bay Trail Construction project will convert the existing on-street trail route into a protected off-street multi-use path utilizing Village-owned right-of-way. The project will improve pedestrian and bicycle safety and provide a more continuous trail connection through the center of Glencoe.
The Village pursued multiple grant opportunities to support construction and was awarded $1,170,720 in funding through the Illinois Department of Transportation’s (IDOT) Illinois Transportation Enhancement Program (ITEP) which supports transportation improvements that expand and enhance non-motorized travel. The awarded ITEP funding will cover approximately 80% of the construction and construction engineering costs, while the Village is responsible for the remaining 20%. Combined with the Village’s Calendar Year 2027 project budget of $350,000, approximately $1.52 million is available to complete the improvements.
Due to the ITEP funding, the project is being bid through IDOT. The project is current...