Legislation Details

File #: 26 -290    Version: 1
Type: Resolution Status: Agenda Ready
File created: 6/9/2026 In control: Board of Trustees
On agenda: 6/18/2026 Final action:
Title: Consideration of a Resolution Ratifying the Village Manager's Prior Execution of a Contract with DiMeo Brothers, Inc. of Elk Grove, Illinois for Emergency Sanitary Sewer Repairs for a Total Cost Not-to-Exceed $35,000
Attachments: 1. VOG Resolution Ratifying Emergency Sewer Repairs, 2. Contract
Agenda Item:
title
Consideration of a Resolution Ratifying the Village Manager's Prior Execution of a Contract with DiMeo Brothers, Inc. of Elk Grove, Illinois for Emergency Sanitary Sewer Repairs for a Total Cost Not-to-Exceed $35,000
memo
Staff Contact: Monica Sarna, Public Works Director
Purpose and Actions Requested: Staff requests Village Board consideration of a resolution ratifying the Village Manager's prior execution of a contract with DiMeo Brothers, Inc. of Elk Grove, Illinois for Emergency Sanitary Sewer Repairs for a total cost not to exceed $35,000
Budget Impact: Unbudgeted
Budget Fund: 130-300-000-80610
Strategic Priority Addressed: Reliable Infrastructure

body
BACKGROUND AND ANALYSIS
As part of its annual maintenance program, the Public Works Sewer Division routinely televises storm and sanitary sewers throughout the Village. During inspections conducted the week of May 18, Public Works staff identified a pavement depression near a storm structure on Sheridan Road between Hazel Avenue and Hawthorn Avenue. Further investigation using the Village's sewer camera equipment revealed a failure of the sanitary sewer main approximately 25 feet below grade.
Due to the depth of the sewer and the complexity of the repair, specialized equipment and expertise were required. The Village's underground utility contractor, Kloepfer Construction, was unavailable to perform the emergency work due to scheduling conflicts. Staff subsequently contacted DiMeo Brothers, the contractor currently performing the Village's water main improvement project, who agreed to assist with the emergency repair for a lump-sum cost of $35,000. Public Works crews supported the effort by providing traffic control, hauling, and disposal services.
On May 27, 2026, Public Works and DiMeo Brothers completed the emergency sanitary sewer repair on Sheridan Road between Hazel Avenue and Hawthorn Avenue. All work was completed the following day, and the Village has finalized payment to Di...