Agenda Item:
title
Review and Discussion of the Draft Village of Glencoe Stormwater Master Plan
memo
Staff Contact: James Tigue, Village Engineer
Purpose and Actions Requested: Staff is requesting the Village Board review the draft Stormwater Master Plan documents and provide feedback to be incorporated into a final draft plan document for review and adoption at a later meeting.
Budget Impact: Budgeted
Strategic Priority Addressed: Reliable Infrastructure, Community Resilience
body
BACKGROUND AND ANALYSIS
Beginning in March 2025, the Village of Glencoe commenced development of a Stormwater Master Plan with Baxter & Woodman, Inc. of Chicago, Illinois. The Stormwater Master Plan is a planning document intended to identify stormwater needs and develop potential projects for prioritization and budgeting purposes. In alignment with the Village’s 2025-2027 Strategic Plan, the Master Plan will support the Reliable Infrastructure goal to ensure a functioning and resilient stormwater network.
The Stormwater Master Plan builds upon the Village’s prior investment in stormwater infrastructure and will provide a roadmap for addressing system components that are reaching or have exceeded their useful life. The Master Plan will help guide the Village’s efforts to adapt to climate change, reduce long-term risk and protect residents and critical assets. Guidance from the Master Plan will allow our team to better plan future investments and will be used as a data set for the development of multi-disciplinary projects around the Village. When used in coordination with previous pavement evaluations, water studies and other infrastructure needs, the Master Plan will help staff create a comprehensive project ranking criteria for future Community Improvement Projects.
The Master Plan development was led by Baxter & Woodman, Inc. with support from Hey & Associates, Inc. This two-year project started with a data collection and analysis phase in 2025. This initial phase included review of the Village’s existing stormwater infrastructure, field investigations, public input survey, an open house meeting and computer modeling to provide an assessment of existing conditions. The second year of the project focused on determining priority project areas, developing potential projects to address identified flooding areas and creating a project evaluation criterion to determine a prioritized ranking. Additionally, ravine assessments, ordinance reviews, evaluation of current operations and maintenance processes and potential funding source evaluations were completed as part of the Master Plan process.
Highlights from the draft Stormwater Master Plan have been incorporated into the project website at www.glencoestormwater.org <http://www.glencoestormwater.org> and comments and feedback on the Master Plan can also be submitted through the website through December 4, 2026.
A summary of the key findings from the draft plan are summarized by topic below:
Existing Conditions Modeling
Most the Village’s stormwater infrastructure dates to the original development of its neighborhoods. The existing conditions analysis utilized updated rainfall data published by the Illinois State Water Survey in 2020, which reflects higher rainfall intensities than those used in previous Village stormwater studies and accounts for changing weather patterns. The modeling results were validated using information collected through the public input survey and staff’s knowledge of historical flooding conditions throughout the community.
Priority Area Identification and Ranking
The study established performance criteria targeting the elimination of flooding greater than six inches in depth adjacent to structures and on roadways. Based on the modeling results, 13 priority improvement areas were identified throughout the Village and ranked according to the severity of structure and roadway flooding. The total estimated cost to implement improvements across all 13 priority areas is approximately $64 million.
Ravine Assessment
Inspections of the Village’s ravines were completed in 2025 and compared with findings from the 2019 Lake Michigan Ravine Inventory. The assessment found no significant changes in erosion or slope stability conditions between the two inspection periods. The study recommends a proactive approach to ravine stabilization and restoration, emphasizing the importance of cooperation among property owners to support long-term ravine preservation.
Ordinance Review
The review found that the Village’s existing stormwater ordinances and development requirements are generally consistent with those of surrounding communities. The Village’s current requirement for stormwater detention on single-family residential properties was identified as an effective stormwater management practice. The study also recommends developing an Engineering Standards Manual to establish consistent technical requirements and guidance for future infrastructure improvements and development.
Operations and Maintenance Review
The assessment recognized the Village’s experienced Public Works staff and extensive institutional knowledge of the stormwater system. Opportunities were identified to further strengthen operations through formalized maintenance procedures, improved documentation and enhanced operational efficiencies. These improvements would support more consistent system management and long-term infrastructure planning.
Project Funding Review
The study identified limited external funding opportunities for stormwater infrastructure improvements. However, incorporating specific project elements aligned with agency priorities may improve eligibility and competitiveness for funding through organizations such as the Metropolitan Water Reclamation District of Greater Chicago (MWRD) and the Illinois Environmental Protection Agency (IEPA). The study also reviewed funding approaches used by neighboring communities, including the establishment of stormwater utility fees to provide a dedicated revenue source for ongoing stormwater improvements.
The Stormwater Master Plan will serve as a critical guidance document for prioritizing infrastructure investments over the next 20 years and beyond. While the estimated costs associated with implementing the identified priority projects are significant, the findings do not indicate a need for immediate, large-scale investment or a fundamental shift in the Village’s approach to stormwater management. The Village has consistently invested in the maintenance and operation of its aging stormwater infrastructure, providing Public Works crews with the equipment and resources necessary to maintain the system effectively. Additionally, several major stormwater improvement projects have been completed over the past decade to address known deficiencies and improve system performance. The Stormwater Master Plan builds upon these ongoing efforts by establishing a long-term framework for prioritizing future improvements, coordinating capital investments and continuing the Village’s proactive approach to stormwater management.
RECOMMENDATION
Staff recommends that the Village Board review and discuss the draft plan document and provide feedback to the planning team that can be incorporated into a final draft plan document. The draft plan is available for public comment through December 4, 2026 and feedback received will be incorporated into a final plan for review and adoption at a later Village Board meeting. Along with staff, the project consultants will provide an overview presentation at the November 19 Committee of the Whole meeting.
ATTACHMENTS
1. Draft Stormwater Master Plan